The Public Authority for Electricity and Water (PAEW) is planning to supply water in Musandam Governorate. The works include:
1) Preliminary and Final design of pipe network with reservoirs and pumping stations construction in Musandam Governorate. The pipe network will cope up with the demand of 2030 with 3 days storage capacity;
2) Work Supervision Services;
3) Supply and installation of Supervisory Control and Data Acquisition (SCADA);
4) Construction of Administration Offices;
5) All associated civil, electrical and mechanical works;
6) preparation of tender, tender analysis, recommendations and contract documents.
1) Review the existing Water Network
2) Perform Hydraulic Study and Network Calculations
3) Prepare preliminary and detailed design and tender documents
4) Coordination with concerned authorities to obtain their approval on the design
5) Construction Supervision